Getting ready for the PT deck pour!
As per below images, we are getting ready for the East Post-Tension concrete slab to be poured on Friday 8/24! We have added an extra...
Mat slab complete!
As of August 10th, we have completed the concrete pouring for the foundation mat slab. The shotcreting for perimeter walls is underway...
Continental Properties sells Voda for $89.5M to Vancouver firm
The new Voda apartments, at 207 Park Lane in Kirkland, sold for $89.5 million, according to King County records. The seller was Kirkland...
Tower Crane Erection: Traffic Control Plan for Monday (7/16)
The tower crane erection is scheduled for Monday (7/16) followed by load testing on Tuesday (7/17). The erection activities will be...
Getting ready for the Tower Crane!
As of this week, The crane base section and embeds are here! The steel reinforcement for crane footings, elevator pit and sand/oil...
Tower Crane goes up on July 7th - Expect periodic street closures
Stream Dexios' tower crane will be erected on Saturday 7/7. The crew will be on site about 5 AM with crane delivery and installation to...
Prior to the Tower Crane Arrival
The project's tower crane will arrive on 7/16. The installation will take two days to complete - one to erect and the second for load...
Piles Complete!
As of Friday, May 18th, all 129 piles have been installed! We'll continue with lagging, excavating and complete the installation of...
Vail Test
Test
Demo in progress!
Demolition of the existing structure at 1600-1612 Dexter Avenue N is in progress and expected to take approximately 3-weeks to complete....